All LPS schools will continue a fully remote learning model until January.

More Information...

For technical support, please submit a ticket.

Newton Middle School

Thanks to the generous support of LPS voters, a new middle school will be built on the Newton campus, while school is in session at Newton. The new school will replace the failing structure and will solve ADA issues, as well as provide the appropriate space for small and large group instruction, creativity and innovation. It will provide space for the LPS NOVA program, which serves students grades kindergarten through 12 with emotional disabilities, and it will include space for professional development for LPS teachers.

A new junior stadium will also be built on the Newton campus. It will provide additional playable surfaces for students in both district-sponsored junior varsity and varsity sports as well as club sports in the community.

New playing fields and parking will be constructed to serve the school, the neighborhood and the junior stadium. The new configuration will provide safer student drop-off and pick-up locations for parents and buses.

Drone Flyover November 2, 2020

Updates

(November 2020) Progress on the new school is currently on-schedule. The asphalt in the parking lot is complete. The learning stair in the cafetorium is currently under construction. Roofing on the gymnasium has been completed, and skylight framing has been completed throughout the school. Cabinetry is currently being installed in the 8th grade wing. 

(July 28, 2020) Over the course of summer 2020, immense progress has been made on the new Newton Middle School, and it is officially 1/3 complete! The building's foundation has been poured, and over 360 concrete piers were drilled and poured. The majority of the underground utilities have been installed, and all concrete slab on grade pours are complete. The gymnasium mansonry is in its final stages, and the cranes onsite are erecting hundreds of steel beams to frame out the classroom wings and main building areas. Stud framing and interior plumbing, electricaly, and HVAC work has begun. Roofing will begin in the next few weeks.

Architect's Fly-Through of the New Newton Middle School

Preliminary Drawings for the New Newton Middle School

Newton drawings, entry November 2019 
Preliminary drawing - main entrance

 Newton drawings, cafetorium November 2019 
Preliminary drawing - cafetorium

 
 


Preliminary drawing - east courtyard

Newton drawings, flex space November 2019
Preliminary drawing - flex space

Newton drawings, typical classroom pod November 2019

Newton drawings, November 2019  Newton drawings, lower level November 2019

November 2018 - January 2019

  • Select architect and engineering firms for the new middle school on the current Newton Middle School campus 
  • Survey the Newton Middle School property

Spring 2019 - Summer 2020

  • Design development of new middle school on Newton Middle School campus
  • Conduct environmental surveys

Spring 2020 - August 2021

Construction of new middle school on Newton Middle School campus

Aerial photograph of Newton Middle School

Aerial photograph of Newton Middle School campus

Projected Grand Opening:  Fall of 2021!